Week 10 – CCM7: Date: Wed (13/07/11); Time: 3-6.00 pm; Venue: EAC Rm (BN lvl2)
Present: Client (Innovatif Bijak Sdn Bhd) – Ir. Zakaria; all members of SLEC and Cyrus companies.
Agenda: - Presentation of company profile (amended)
Cyrus company (group 3) presents first
SLEC company (group 2) presents second
Minutes: -
Areas of weakness were outlined by Ir. Zakaria for both groups
- Minutes were all noted down by Head Department of Water and Sewerage, Ir. Teh Chin Hooi.
- The main areas to decide the main layout.
- Discussion and compared on both layout.
- Submission of preliminary report on this week.
PM:
- Lifelong learning
- Report of sustainability
- Choose Layout 1
- Matrix Table
- DOB cost
Structural
- No Task
- Present Sustainability and Lifelong learning next presentation.
Water & Drainage
- Drawing not compile with the others
Highway & Environmental
- Sustainability and Lifelong Learning in next Presentation
Geotechnical
- There are 4 types of soil, determine it. (For example: USM etc.)
- Check the flood level with drainage department.
- Work on Foundation.