Week 9 – CCM8: Date: Wed (20/07/11); Time: 3-5.00 pm; Venue: EAC Rm (BN lvl2)
Present: Client (Innovatif Bijak Sdn Bhd) – Ir. Zakaria; 4 members of SLEC and 2 members of Cyrus companies.
Agenda: - Presentation of company profile (amended)
SLEC company (group 2) presents first
Cyrus company (group 3) presents second
Minutes: -
Areas of weakness were outlined by Ir. Zakaria for both groups
- Minutes were all noted down by Head Department of Water and Sewerage, Ir. Teh Chin Hooi.
- The main areas to discuss about the long-life learning and sustainability of project.
- Changes for preliminary report submit on this week.
PM:
- In the matrix table, only show sustainablity(remove life-long learning), modify into technical feasibility
- Add in structural cost and valve cost.
- Show Spefication of contract in preliminary report, bill of quantity and mention the type of contract
Structural
- Rearrange lifelong learning according to the sequence of importance.
Water & Drainage
- Present valve and manhole in next CCM
- Modify the Lifelong learning
- Location of suction tank to be confirm.
Highway & Environmental
- Calculate traffic to determine 1 lane or 2 lane.
- Usually when come in is 1 lane but go out is 2 lane.
- Show Stop or Berhenti?
- Road for STP should be 1 lane
- Present Environmental Management Plan (EMP) in next ccm.
Geotechnical
- ABSENT.
General comment in Cyrus Companies.
- Use term of Shallow Foundation and Deep Foundation.
- Usage of drill pile and micro-pile.